A division of     

 
 

Recent Projects

Headframe and Hoisting Upgrade, Saskatchewan

 

This project involved the installation of the world’s largest AC Drive friction hoist. Cook Engineering was chosen to design the structure to support the new hoist, to modify the shaft as required to accommodate the new 50 ton, 75 ft long skips, to design the 50 ton loading flasks to load the skips and the ancillary building systems. The new structure was designed to be independently mounted above and straddling the existing 260 ft high headframe (also designed by Cook Engineering over 40 years ago). This allowed production to continue during construction with a minimum shutdown for hoist changeover.

 

This project has been in operation since 2005. This unique design approach is currently being duplicated on two additional headframe upgrade designs currently underway for the Potash industry.

 

 

 

 

Power Boiler Upgrade, Thunder Bay , Ontario

 This boiler upgrade project consisted of modifications to the biofuel processing and metered feed systems, new lower furnace, grate and over-fire combustion air systems, combustion controls and a new ash handling system.  The project successfully minimized the use of fossil fuel in the boiler by eliminating biofuel firing outages during grate ash removal and, by providing vastly improved biofuel firing control, allowed the boiler to respond to mill process demand swings without using fossil fuel. 

Cook Engineering worked as part of a design-build team, consisting of a contractor, EKT-90 Inc, and Alstom Power.  The multi-discipline Cook team was responsible for the design of the biomass fuel infeed, preparation and metering system from the yard to the windswept spout fuel distributors on the boiler, the ash system design, including an innovative adaptation of ash conditioning technology, and structural design for the Detroit Stoker VCG grate and other boiler ancillaries.   The project required an innovative approach to construction, with the grate foundation being installed beneath the operating boiler to reduce the length of the boiler outage.

The system has been contributing to the reduction of greenhouse gases since 2005.

The project was the subject of a Pulp and Paper Canada article in Oct/Nov. 2009.

 

Island Drive Bridge, Thunder Bay

 

Cook Engineering provided civil, structural, electrical and environmental engineering design services for this bridge as part of a design-build team. The structure is the longest integral abutment bridge in Canada.  The integral abutment concept accommodates the thermal movement of the bridge by deflecting the abutments in combination with the piling. This eliminates the need for expansion joints over any of the structural girders and therefore reduces the maintenance issues associated with these components. This approach provides the capability of accepting larger thermal displacements at each abutment. 

 In terms of the total thermal displacement, it is believed that this structure experiences the largest overall movements of any integral abutment bridge in North America.

 

TERRACE BAY PULP INC
Detailed engineering for 875 psig steam supply and 75 psig exhaust piping associated with a 25 MWe back-pressure steam turbine installation as part of a biofuel cogeneration plant.
 

MTO BRIDGE INSPECTIONS
Large-scale bridge inspection assignment involving more than 120 bridges & culverts on the Trans-Canada Hwy and other highways and local roads throughout Northwestern Ontario.

ZELSTOFF CELGAR Castlegar, B.C.
Detailed engineering associated with a 48 MWe condensing steam turbine installation, steam savings associated with implemen- implementation of a number of pinch projects, and a power boiler upgrade.

 

 
LEGAL | COPYRIGHT

V.B. Cook Co. Limited, Engineers & Architect